4000 square meters of scaffolding. 50% of the project erected with aluminium tubes to significantly reduce the weight of the structure. Weekly inspections were carried out during the whole project by our advanced scaffold inspector.

Project was built in two stages.

100m protective fan

Project completed on time within the program supplied by the client.

This project for the Czech Republic Embassy had strict guide lines in the heart of Nothing Hill Gate.

Security was essential and a very high volume of public to be guided and kept safe while works were being carried out.

The project was to clean brickwork and replace windows without incidents and completed  on time.

The 100m fan was erected out of hours because of less public traffic at our cost rather than the client. Safety first at Q.